How to visualize linked dependency statuses at scale

Aha! Roadmaps

If you depend on multiple cross-functional teams to help implement your strategic roadmap — or if you are a platform team serving multiple product teams in addition to your own strategic commitments — it can be difficult to see the status of all work in progress at once. Gantt charts can visualize dependencies between work in releases or epics, but are difficult to read when there are a large number of items in flight. The dependency report can handle a large number of items, but has trouble highlighting at-risk dependencies.

Custom roadmap showing status of linked dependencies.

The best solution for dependency statuses at scale will show you the status of all dependencies across multiple teams at a glance. In this article, we will build one together using calculation columns and a custom roadmap. Follow along and give it a try!

The custom roadmap can also show dependency lines. In this article, we want to build a roadmap to make those dependencies' status more visually expressive.

Click any of the following links to skip ahead:

Confirm user permissions

Action

User permissions

Create reports and roadmaps

Viewer

View dependencies across workspaces

Viewer

Note: You can view dependencies for any workspace that you have access to.

Top

Create a list report of dependent records

First, we need to create a list report of dependent records. For our example, we are going to use features. Navigate to Roadmaps -> List to get started, then click Create new report.

List report showing features and dependent features linked to them.

  • In the Add fields step of the report builder:

    • Add the following fields to the Features table:

      • Name

      • Assigned to

      • Start date

      • Due date

      • Status

      • Workspace name

    • Click Add records related to feature and select Feature record links and add the following field:

      • Linked type

    • Click Add records related to feature record links and select Linked feature, then add the following fields.

      • Name

      • Assigned to

      • Start date

      • Due date

      • Status

  • In the Add filters step, add any filters you need to see the features and linked dependent features that are critical to your team's roadmap. We will add:

    • Workspace name: Filtered to our team's workspace.

    • Feature status: Filtered to all features that are Not started or In progress. We want to remove any shipped features from the report.

    • Record linked type: Filtered to Depends on.

Click Create report to create the list report.

Top

Add calculation columns

Next, we need to create two calculation columns. The first will calculate the difference between the due dates for dependent records. The second will sort those differences into two statuses, so we can see if the feature is on track or at risk.

List report of features and linked dependent features with calculation columns for datediff and dependency status.

To do this, click the (+) button on the far right of the list report, and Add these Calculation columns:

  • Add a Datediff calculation with the following equation: datediff(field("Feature due date"),field("Linked feature due date"),"day").

  • Add a Dependency status calculation with the following equation (where "Date Diff" is the name of your first calculation column): if(field("date diff")<0,"On track","At risk").

These calculation columns are just one way to flag and manage at-risk work. Use delivery risk indicators (automated and manual) to highlight risks at key points in your team's development workflow.

Top

Convert your report to a custom roadmap

We now have a way to see for each individual feature whether its dependent record is expected to be completed before or after its scheduled due date. This is already insightful — but is still too granular for an overview. For our next step, let's convert the list report to a custom roadmap.

Custom roadmap showing linked dependencies

To do this, we do not need to create a custom roadmap from scratch. Select Roadmap from the Change view type dropdown in the upper left to convert the list report data to a custom roadmap.

  • The Record hierarchy we created for the list report is still applied to the custom roadmap. We can skip this step.

  • For Type, select Bars.

  • For the bars' Start and End dates, select the linked features' Start and Due dates.

  • Show on bars the Linked feature name, Linked feature assignee, and the first calculation column (the Date diff calculation).

  • Group the bars by Workspace name, Feature name, Feature status, Feature assigned to, and Feature start date.

Click Save to create the custom roadmap.

Top

Customize your roadmap

Finally, we need to customize the roadmap so it highlights the dependency status. To do this, open the Configure sidebar on the right side of the page.

  • Color by the second calculation column, Dependency status. You can further customize the status colors — say, a red for At risk and a green for On track.

  • Check the box to include Progress on the bars. Then when a linked feature is At risk, we can see how close it is to completion.

Custom roadmap showing status of linked dependencies.

Congratulations! We now have a single page view that shows — even at scale — the dependency status of every feature on our roadmap. Save this roadmap to include it in presentations and dashboards, or to schedule regular email delivery to interested stakeholders like executives or heads of other product teams.